Construction of Parking Area at Saham Hospital
Client: North Al Batinah Governorate – North Al Batinah MunicipalityProject Value: OMR 151,410.000Completion Status: Completed Scope of Work: Parking area development Interlock and pavement works
Rehabilitation of Service Road at Suhar
Client: North Al Batinah Governorate – North Al Batinah MunicipalityProject Value: OMR 459,483.000Completion Status: Completed Scope of Work: Service road rehabilitation Asphalt resurfacing Drainage and
Design and Construction of Expressway Access Road
Client: North Al Batinah Governorate – North Al Batinah MunicipalityProject Value: OMR 612,065.349Completion Status: Completed Scope of Work: Access road construction Asphalt and pavement works
Rehabilitation of Damaged Roads (Emergency Work)
Client: North Al Batinah Governorate – North Al Batinah MunicipalityProject Value: OMR 349,419.000Completion Status: Completed Scope of Work: Emergency road restoration Pavement repair and strengthening
Maintenance of Internal Roads at Shinas
Client: North Al Batinah Governorate – North Al Batinah MunicipalityProject Value: OMR 1,157,364.000Completion Status: Completed Scope of Work: Road maintenance and rehabilitation Asphalt paving and
Maintenance of Internal Roads in Saham
Client: North Al Batinah Governorate – North Al Batinah MunicipalityProject Value: OMR 1,199,843.000Completion Status: Completed Scope of Work: Rehabilitation and maintenance of roads Asphalt resurfacing
Extension of Car Sale Complex in Suhar
Client: North Al Batinah Governorate – North Al Batinah MunicipalityContractor: Suhar Developer SPCProject Value: OMR 1,586,489.000Duration: 01 October 2024 – 01 May 2026Status: Work In
Construction of Internal Roads for Compensation Area at Suhar
Client: North Al Batinah Governorate – North Al Batinah MunicipalityContractor: Suhar Developer SPCProject Value: OMR 2,068,823.000Duration: 03 November 2024 – 18 December 2026Status: Work In
Design and Construction of Internal Roads at Suhar (Balance Area)
Client: North Al Batinah Governorate – North Al Batinah MunicipalityContractor: Suhar Developer SPCProject Value: OMR 2,043,950.000Duration: 15 September 2025 – 15 October 2026Status: Work In
Development of Liwa Entrance
Client: North Al Batinah Governorate – North Al Batinah MunicipalityContractor: Suhar Developer SPCProject Value: OMR 2,117,954.000Duration: 01 June 2025 – 01 June 2026Status: Work In